We are doing everything we can to ensure we have continuity of business, while heeding the very latest Government advice. We monitor this daily and adapt our procedures and messaging immediately to any changes that are required. We would like to express our sympathies to everyone who has been affected and continues to be affected by the COVID-19 virus.

We would also like to show our support to our teams and key workers who are working tirelessly across the country.

For more about how Willmott Dixon group are responding to the everyday changes of Covid-19 please click here.

Imperial College London - Library Phase 1

Refurbishment of the Imperial College of London’s library at the Kensington campus
_2

Project Stats

Duration
7 weeks
Value
£3.5million
Size
10,334 sq ft
Sector
Education

Project Story

This project had a number of inbuilt challenges. Firstly, the O&M manuals were not current which made surveying critical to understanding the building as it stood. Secondly, the risers were congested with services, so we needed a safe environment in which to work. To combat this, we installed safety points on a sheer wall, which after testing enabled our site team to clip on to a harness to work on the services. Identifying and managing risk with the strong PM and QS team made the project run smoothly. We were extremely proud to deliver this project in just 7 weeks, especially as at several points in the project the team had to amend the design swiftly to meet the customers' needs.
Project Outcomes
  • Completed project on a live site with limited noisy working hours
  • Satisfying all the stakeholders in this multi-tenanted live building with no complaints
  • Ongoing customer relationships and opportunities

Project Team

Consultant team
Architect: BDP
Project Manager: Turner & Townsend
Cost Consultant: Arcadis
Services Engineer: Jacobs