Travelodge Rollout - Nationwide

Rollout Framework for the renowned hotel chain

Project Stats

Duration
60 months ongoing
Value
£28million
Size
8,208 keys
Sector
Hotels

Project Story

Following a successful three-year Framework agreement for a National Refresh Programme, we were extremely proud to be appointed by Travelodge for a further two-year programme. The works required a refresh of each individual hotel which had to be carried out while it was open to the public. We therefore had to create an innovative and complex phasing programme in order to minimise disruption to residents and the Travelodge staff.
Project Outcomes
  • National multi-site refurbishment programme
  • 8,208 individual guest rooms completed
  • Successful long-term partnership
  • Average delivery of 20 rooms every 5 days per site

Project Team

Graham Shaw × Managing Director
Paul Gorry × Principal Sales & Marketing Manager
Consultant team
Customer: Travelodge
Cost Consultant: Wakemans

Other Projects

Contact us

Like what you see? Want to work with our amazing team? Contact us today
Contact us