We are doing everything we can to ensure we have continuity of business, while heeding the very latest Government advice. We monitor this daily and adapt our procedures and messaging immediately to any changes that are required. We would like to express our sympathies to everyone who has been affected and continues to be affected by the COVID-19 virus.

We would also like to show our support to our teams and key workers who are working tirelessly across the country.

For more about how Willmott Dixon group are responding to the everyday changes of Covid-19 please click here.

Travelodge Sleepy Hollow

Upgrade of Travelodge's head quarters building
_2

Project Stats

Duration
26 weeks
Value
£1.3million
Size
25,833 sq ft
Sector
Commercial

Project Story

Following a successful five year Framework agreement for a National Refresh Programme, we were proudly appointed to this prestigious upgrade whilst in occupation. Our works comprised of air conditioning upgrades, improvement of the lift car and the installation of new flooring, ceilings and decorations. Our external works included external painting to the facade and associated repairs, plus minor roofing works.
Project Challenges
  • Working in a live environment alongside Travelodge employees
  • Phased completion to minimise disruption to employees

Project Team

Consultant team
Cost Consultant: Wakemans

Other Projects

Contact us

Like what you see? Want to work with our amazing team? Contact us today