Project Stats
Duration
37 weeks
Value
£5.3million
Size
197 keys
Sector
Hotels
Project Story
The phased works, whilst in occupation included the strip-out and refurbishment of each guest room, the upgrade of all M&E, new case goods, wall linings, FF&E and a complete refresh of the bathrooms. In addition to the hotel rooms, we redecorated the lobby and hallway spaces throughout, giving the hotel a fully refurbished feel and enhanced customer experience. We are thrilled to have succeeded in delivering across our customer's quality, budget and programme requirements. The Cambridge City Hotel now have an offering that stands out amongst its competition and we were extremely proud that the works were carried out under a 'Design & Build' contract in just 37 weeks.
Project Outcomes
- Delivery of high quality finishes to 4*+ standard
- Phased project in occupation
- Successful liaison with hotel management to manage restricted working conditions
- Delivered within time and budget restraints
Project Team
Consultant team
Architect: Bevis Design Architects
Project Manager: Jones Lang LaSalle
Cost Consultant: Jones Lang LaSalle
Services Engineer: Building Service Design